Installation Steps 

 

  1. Check all electrical connections and ensure all cables are securely fastened.
  2. Install the 30A Fuse into the fuse holder, ensure the fuse holder is securely fastened.
  3. Remove the opaque material from the solar panels.
  4. Follow the PWM 30 operating steps.

Products covered in this article: Overlander/Overlander (E)/Retreat/Retreat (E)/Weekender/Solar Elite/Solar Extreme Solar Kits